Sills
     As the water continues to leak down through the wall, it eventually ends up in the sill and roughly one third of the sill on the southern end east side was rotted and needed replacement. Several joists also needed replacing.
Sill SE Corner
SE corner with rotted sill
Left Arrow
 
 
Post & replaced sill
Right arrow
New sill and post
     
Sill Replacement
Replaced sill & joists
Left Arrow
 
 
Replaced joist in old sill
Right arrow
Sill & new joist
Left Arrow Left Center Post   Right Arrow